Course
İYHD1243580
MANAGEMENT of VARIATIONS
- LECTURE
- 3
- LAB
- 0
- CREDITS
- 3
- ECTS
- 8
AIM
This course aims to provide a framework for the efficient, consistent and efficient identification and evaluation system of variations in a contract – especially time and cost related variance throughout the construction industry.
CONTENT
This course contains; Changes in contracts: Introduction,Formal changes: The Changes Clause,The contents of the Changes Clause,Valuation of Changes,Negative changes,Cardinal changes,Changes and pricing arrangements,Midterm exam study,Case study,Constructive changes,Design errors and errors in specifications,Erroneous rejection,Overinspection and disruption,Case study.
LEARNING OUTCOMES
- 1
Understands contract obligations related to changes.
Taught by: Problem Solving Method, Question - Answer Technique, Problem Baded Learning Model, Inquiry-Based Learning, Lecture Method · Assessed by: Traditional Written Exam, Homework, Quiz
- 2
Gains skills in change management.
Taught by: Problem Solving Method, Question - Answer Technique, Problem Baded Learning Model, Inquiry-Based Learning, Lecture Method · Assessed by: Traditional Written Exam, Homework, Quiz
- 3
Obtains a thorough understanding of the scope of work.
Taught by: Problem Solving Method, Question - Answer Technique, Problem Baded Learning Model, Inquiry-Based Learning, Lecture Method · Assessed by: Traditional Written Exam, Homework, Quiz
- 4
Understands how changes occur.
Taught by: Problem Solving Method, Question - Answer Technique, Problem Baded Learning Model, Inquiry-Based Learning, Lecture Method · Assessed by: Traditional Written Exam, Homework, Quiz
- 5
Understands the consequences of changes.
Taught by: Problem Solving Method, Question - Answer Technique, Problem Baded Learning Model, Inquiry-Based Learning, Lecture Method · Assessed by: Traditional Written Exam, Homework, Quiz
WEEKLY PLAN
- WEEK 1
Changes in contracts: Introduction
- WEEK 2
Formal changes: The Changes Clause
- WEEK 3
The contents of the Changes Clause
- WEEK 4
Valuation of Changes
- WEEK 5
Negative changes
- WEEK 6
Cardinal changes
- WEEK 7
Changes and pricing arrangements
- WEEK 8
Midterm exam study
- WEEK 9
Case study
- WEEK 10
Constructive changes
- WEEK 11
Design errors and errors in specifications
- WEEK 12
Erroneous rejection
- WEEK 13
Overinspection and disruption
- WEEK 14
Case study
ASSESSMENT
- Rate of Midterm Exam to Success50%
- Rate of Final Exam to Success50%
WORKLOAD
| ACTIVITY | COUNT | HOURS | TOTAL |
|---|---|---|---|
| Course Hours | 14 | 3 | 42 |
| Guided Problem Solving | 0 | 0 | 0 |
| Resolution of Homework Problems and Submission as a Report | 12 | 3 | 36 |
| Term Project | 2 | 20 | 40 |
| Presentation of Project / Seminar | 4 | 10 | 40 |
| Quiz | 1 | 10 | 10 |
| Midterm Exam | 1 | 20 | 20 |
| General Exam | 1 | 40 | 40 |
| Performance Task, Maintenance Plan | 0 | 0 | 0 |
READING
- Michael T. Callahan, Construction Change Order Claims,Aspen Publishers Online, 2005 Paul Levin (ed.), Construction Contract Claims, Changes, and Dispute Resolution 3rd Revised edition, American Society of Civil Engineers, 2016
TEACHING STAFF
- Prof.Dr. Ayşe Zeynep SÖZENCOORDINATOR
- Prof.Dr. Ayşe Zeynep SÖZEN